Annex 2
WHO guidelines on quality risk management
1. Introduction
1.1 Background and scope         62
1.2 Principles of quality risk management         64
2. Glossary         67
3. Quality risk management process         70
3.1 Initiating a QRM process         70
3.2 Personnel involved in QRM         70
3.3 Knowledge of the product and process         71
3.4 Risk assessment         71
3.5 Risk control         72
3.6 Risk review         73
3.7 Verification of QRM process and methodologies         74
3.8 Risk communication and documentation         75
4. QRM application for pharmaceuticals         76
4.1 Training and education         76
4.2 Responsibilities         76
4.3 QRM application during product development         77
4.4 QRM application during validation and qualification         78
4.5 QRM application during commercial manufacturing         79
4.5.1 QRM integration with key quality system elements         79
4.5.2 QRM application in product manufacturing operations         80
5. QRM considerations for medicines regulatory authorities         81
5.1 Introduction         81
5.2 QRM application to inspection strategy         82
5.2.1         Risk management in inspections 82
5.2.2         Inspection planning and conduct 82
5.2.3         Corrective action and preventive action review, and scheduling of  routine inspections 83
5.2.4         Complaint handling and investigation 83
5.3 Inspection of QRM at a manufacturing site         83
5.4 QRM applied to dossier review (assessment)         85
6. Risk management tools 87 References 91
1. Introduction
Background and scope
In most countries compliance with good manufacturing practices (GMP) (1, 2) (including validation), medicines regulatory activities and inspections, together with supply chain controls throughout the product life-cycle, provide good assurance that risks are largely controlled. However, where control is less effective, patients may be put at risk through the production of medicines of inadequate quality. The assessment of individual risks related to specific products and starting materials and the recognition of hazards at specific stages of production or distribution should permit regulatory authorities to improve control of medicines by increasing the effectiveness of their activities within the limits of the available resources. Quality risk management (QRM) is a process that is relevant to all countries and should provide a rationale to understand risk and mitigate it through appropriate and robust controls.
The aim of these guidelines is to assist the development and implementation of effective QRM, covering activities such as research and development, sourcing of materials, manufacturing, packaging, testing, storage and distribution. In the past, hazard analysis and critical control point (HACCP) methodology, traditionally a food safety management system but subsequently applied to other industries, has been the basis of WHO risk management guidance to the pharmaceutical industry (3).
More recently international guidance has emerged (2, 4–7) that is of specific relevance to the pharmaceutical industry and which addresses the full scope of pharmaceutical industry QRM more effectively than HACCP principles, including how to structure regulatory filings using a risk-based approach. Consequently, these WHO guidelines have been developed as an update on WHO's advice to the pharmaceutical industry, taking account of this new guidance.
To protect patients in terms of quality, safety and efficacy of medicines, international medicines regulatory authorities (MRAs) are recommending pharmaceutical manufacturers to adopt a risk-based approach to the life-cycle of a pharmaceutical product. Some MRAs require the adoption of a risk-based approach for specific areas in the life-cycle of a pharmaceutical product, e.g. environmental monitoring in sterile products manufacture. The level of QRM activity and the density of associated documentation will evolve as the product progresses from early development through to routine production.
QRM is the overall and continuing process of appropriately managing risks to product quality throughout the product's life-cycle in order to optimize its benefit–risk balance. It is a systematic process for the assessment, control, communication and review of risks to the quality of the medicinal product. It can be applied both proactively and retrospectively.
While the choice of the tools to support the QRM approach is optional and may vary, the tools chosen need to be appropriate for the intended use.
In return for using this approach, there are potential opportunities for both MRAs and pharmaceutical manufacturers (8) as summarized in the following sections.
■ Quality risk management (QRM) principles can be applied to both MRAs and pharmaceutical manufacturers:
?        MRAs: systematic and structured planning of reviews and inspections that are risk-based. The submission review and inspection programmes can also operate in a coordinated and synergistic manner.
?        Manufacturers: design, development, manufacture and distribution, i.e. the life-cycle of a pharmaceutical product. QRM should be an integral element of the pharmaceutical quality system (QS).
?        ■ Science-based decision-making can be embedded into QRM processes:
?        MRAs: decisions regarding review, inspection or inspection frequency should consider product risk and GMP compliance of the manufacturer. The MRA accepts residual risks through understanding the QRM decisions involved.
?        Manufacturers: quality decisions and filing commitments can be based on a science-based understanding of the process and QRM (when using the quality by design approach, and other approaches where appropriate). Its effective application should offer manufacturers greater freedom to decide how to comply with the principles of GMP and this, therefore, should encourage innovation.

The control strategy for the process focuses on critical quality attributes and critical process parameters.
■ Resources can be focused on risks to patients:
?        MRAs: QRM can be used to determine the best allocation of inspection resources, both in terms of product types and for specific areas of focus for a given inspection. This enables the most efficient and effective scrutiny of the most significant health risks. Those manufacturers with poor histories of GMP compliance can also be more closely and frequently evaluated by on-site inspection than those manufacturers with better records.
?        Manufacturers: evaluation of quality risk through science-based decisions can be linked ultimately to protection of the patient by ensuring the quality, safety and efficacy of the product. A corporate culture is supported to produce cost-effective medicines, without compromising quality, while maintaining the focus on the patient as a primary stakeholder in all activities.
?        ■ Restrictive and unnecessary practices can be avoided:
?        MRAs: regulatory scrutiny should consider the level of risk to patients. Improvement and innovation by manufacturers should be encouraged.
?        Manufacturers: instead of having systems designed to inhibit change and minimize business risk, changes can be managed within a company's quality management system. Innovation and the adoption of the latest scientific advances in manufacturing and technology are supported. Unnecessary testing can be eliminated, for example, with real-time release testing.
?        ■ Communication and transparency are facilitated:
?        MRAs: facilitate dialogue with pharmaceutical manufacturers and communicate clearly to the industry and the public how the inspection programme may be adjusted based on the risk to patients. Information-sharing between MRAs will contribute to a better risk management approach globally.
?        Manufacturers: matrix team approach, stakeholders are kept informed through science-based decisions. This builds a culture of trust and a “one-team” mindset with a focus on the product and the patient.

These guidelines will align with the general framework described in other current international guidance on this subject.
1.2 Principles of quality risk management
It is not always appropriate nor always necessary to use a formal risk management process (using recognized tools and/or internal procedures, e.g. standard operating procedures (SOPs)). The use of an informal risk management process (using empirical tools or internal procedures) can also be considered acceptable.
The two primary principles of QRM are that:

■ The evaluation of the risk to quality should be based on scientific knowledge and ultimately linked to the protection of the patient.
■ The level of effort, formality and documentation of the QRM process should be commensurate with the level of risk.

In addition to the two principles above, the following principles are also part of the QRM methodology:
■ When applied, processes using QRM methodologies should be dynamic, iterative and responsive to change.
■ The capability for continual improvement should be embedded in the QRM process.

This guidance describes the WHO approach to QRM, using the concepts described in ICH Q9 (6) and illustrated in Figure 1. The emphasis on each component of the framework might differ from case to case but a robust process will incorporate consideration of all the elements at a level of detail that is commensurate with the specific risk.
Figure 1
Overview of a typical quality risk management process

Reproduced from reference 5: ICH Q9: Quality Risk Management.
Decision points are not shown in the diagram above because decisions can occur at any point in the process. The decision might be:
■ to return to the previous step and seek further information;
■ to adjust the risk models; or even
■ to terminate the risk management process based upon information that supports such a decision.

The approach described in these guidelines may be used to:
■ systematically analyse products and processes to ensure that the best scientific rationale is in place to improve the probability of success;
■ identify important knowledge gaps associated with processes that need to be understood to properly identify risks;
■ provide the communication process that will best interface with all relevant parties involved in the QRM activities;
■ facilitate the transfer of process knowledge and product development history to ease product progression throughout its life-cycle and to supplement already available knowledge about the product;
■ enable the pharmaceutical industry to adopt a risk-based approach to development as described in regulatory guidance (4–6). The QRM outputs will potentially serve as reference documents to support product development and control strategy discussions in regulatory filings.

Early in development, the purpose of the QRM process may be to acquire sufficient product and process knowledge to assess risks associated with formulation development of the finished pharmaceutical product (FPP) according to the quality target product profile (QTPP). In recognizing risks and knowledge gaps, the QRM process plays a significant role in proactively enabling the prioritization and mitigation of risks. The objective is to develop the FPP through maximizing product and process knowledge and risk mitigation.
As FPP development progresses, in addition to supporting that development, the purpose of the QRM process is to determine and manage risks to bioavailability, safety, efficacy and product quality. QRM in development should differentiate process parameters and quality attributes from critical process parameters (CPPs) and critical quality attributes (CQAs), thereby contributing to defining and refining the control strategy.
The long process of product development is inevitably complex and requires the continual exchange of data, decisions and updates both internally within companies and, where required, with external stakeholders, such as MRAs. A crucial aspect of product development and QRM is the maintenance of an effective and secure knowledge management and documentation system. Such a system must facilitate transparent communication and the highlighting of key issues to stakeholders and must also include a well-structured archive. Clearly, the ability to organize diverse data and information effectively and then retrieve it as required for updating and further evaluation, e.g. for the purposes of process validation, would be hugely beneficial.
Finally, it should be noted that QRM activities are focused on the product/ process development and product manufacturing, ultimately to ensure a robust, safe and effective FPP.
2. Glossary
The definitions given below apply to the terms used in these guidelines. They may have different meanings in other contexts.
control strategy
A planned set of controls, derived from current product and process understanding that assures process performance and product quality. The controls can include parameters and attributes related to active pharmaceutical ingredients (APIs) and finished pharmaceutical product (FPP) materials and components, facility and equipment operating conditions, in-process controls, finished product specifications, and the associated methods and frequency of monitoring and control.
critical quality attribute (CQA)
A physical, chemical, biological or microbiological property or characteristic that should be within an appropriate limit, range, or distribution to ensure the desired product quality.
failure mode
Different ways that a process or subprocess can fail to provide the anticipated result.
failure mode, effects and criticality analysis (FMECA)
A systematic method of identifying and preventing product and process problems.
finished pharmaceutical product (FPP)
A finished dosage form of a pharmaceutical product that has undergone all stages of manufacture, including packaging in its final container and labelling.
formal experimental design
A structured, organized method for determining the relationship between factors affecting a process and the output of that process. Also known as “design of experiments”.
occurrence
Probability of negative events within a fixed time frame.
pharmaceutical product
Any material or product intended for human or veterinary use presented in its finished dosage form or as a starting material for use in such a dosage form, that is subject to control by pharmaceutical legislation in the exporting state and/or the importing state.
pharmaceutical product target profile (PPTP)
A definition of the target properties of the FPP, including dosage form and strength(s), route of administration and relevant drug release and pharmacokinetic requirements.
planned risk assessment
An assessment that is conducted in advance of an activity, either before any work is conducted or before further work is conducted. This enables quality to be built into activities and risk to be reduced, e.g. design of high containment facilities for manufacture of cytotoxic products.
process robustness
Ability of a process to tolerate variability of materials and changes of the process and equipment without negative impact on quality.
qualification
The action of proving and documenting that any premises, systems and equipment are properly installed and/or work correctly and lead to the expected results. Qualification is often a part (the initial stage) of validation, but the individual qualification steps alone do not constitute process validation.
quality critical process parameter
A process parameter which could have an impact on the critical quality attribute.
quality risk management
A systematic process for the assessment, control communication, and review of risks to the quality of the pharmaceutical product across the product life-cycle.
risk
Combination of the probability of occurrence of harm and severity of the harm.
risk analysis
The estimation of the risk associated with the identified hazards.
risk assessment
A systematic process of organizing information to support a risk decision to be made within a risk management process. It consists of the identification of hazards and the evaluation of risk associated with exposure to those hazards.
risk control
The sharing of information about risk and risk management between the decision-maker and other stakeholders.
risk evaluation
The comparison of the estimated risk to given risk criteria using a quantitative or qualitative scale to determine the significance of the risk.
risk identification
The systematic use of information to identify potential sources of harm (hazards) referring to the risk question or problem description.
risk priority number (RPN)
A numeric assessment of risk assigned to a process, or steps in a process, as part of failure mode effects analysis (FMEA). Each failure mode gets a numeric score that quantifies likelihood of occurrence, likelihood of detection and severity of impact. The product of these three scores is the RPN for that failure mode. RPN = severity rating × occurrence rating × detection rating.
risk review
Review or monitoring of output or results of the risk management process considering (if appropriate) new knowledge and experience about the risk.
stakeholder
Any individual, group or organization that can affect, be affected by, or perceive itself to be affected by a risk. Primary stakeholders are the patient, health-care professional, MRAs and the pharmaceutical industry.
unplanned risk assessment
An assessment that is conducted to assess the impact of a situation that has already occurred, e.g. impact of a deviation from normal ways of working.
validation
The documented act of proving that any procedure, process, equipment, material, activity or system actually leads to the expected results.
verification
The application of methods, procedures, tests and other evaluations, in addition to monitoring, to determine compliance with the quality risk management activities.
3. Quality risk management process
Initiating a QRM process
QRM activities should be performed using systematic processes designed to coordinate, facilitate and improve science-based decision-making with respect to risk. The possible steps to be taken in initiating and planning a QRM process might include the following (5):
■ define the problem and/or risk question, including pertinent assumptions identifying the potential for risk;
■ assemble background information and/or data on the potential hazard, harm or human health impact relevant to the risk assessment;
■ identify a leader and the necessary resources;
■ specify a timeline, the deliverables, and an appropriate level of decision-making for the risk management process.

Internal SOPs should define steps, stakeholders, roles and responsibilities (governance and management responsibilities).
3.2 Personnel involved in QRM
The implementing party, i.e. the pharmaceutical manufacturer or regulatory authority, should assure that personnel with appropriate product-specific knowledge and expertise are available to ensure effective planning and completion of QRM activities. This may be best accomplished by assembling a multidisciplinary team according to the guidance provided in section 4.2.
The personnel appointed should be able to:
■ conduct a risk analysis;
■ identify and analyse potential risks;
■ evaluate risks and determine which ones should be controlled and which ones can be accepted;
■ recommend and implement adequate risk control measures;
■ devise procedures for risk review, monitoring and verification;
■ consider the impact of risk findings on related or similar products and/or processes.

QRM activities should be defined and documented.
3.3 Knowledge of the product and process
QRM should be based on knowledge of the product or processes concerned, according to the stage of the product life-cycle.
A flow diagram may be helpful, covering all operations and controls in the process under evaluation. When applying QRM to a given operation, the steps preceding and following that operation should also be considered. A block-type diagram may be sufficiently descriptive. Amendments to the flow diagram may be made where appropriate, and should be documented.
3.4 Risk assessment
When risk assessment is conducted, safety and efficacy need to be considered in addition to the quality concerns.
During the assessment all the risks that may reasonably be expected to occur when conducting the activity under evaluation should be listed. This is usually done when the risk assessment is made for the first time, i.e. initiated, when there is a change or a concern and may also be applied to existing processes. An analysis should be conducted to identify which risks it is essential to eliminate or to reduce to acceptable levels.
A thorough risk assessment is required to ensure effective risk control. Risk assessment should review the materials, operations, equipment, storage, distribution and intended use of the product. Typically a list of the potential risks (biological, chemical and physical) which may be introduced, increased or controlled in each area should be drawn up. In the risk assessment the following basic questions should be addressed:
■ What might go wrong?
■ What is the nature of possible risks?
■ What is the probability of their occurrence and how easy is it to detect them?
■ What are the consequences (the severity)?

It should then be decided which of the potential risks should be addressed by the QRM activities and what control measures, if any, should be taken for each risk. If a risk has been identified at a step where control is necessary for safety, and no control measure exists at that step or at any other, the product or process should be modified at that step, or at an earlier or later stage, to include such a control measure. More than one control measure may be required to control a specific risk and more than one risk may be controlled by a specified control measure.
Options for risk assessment methodologies are described in section 5.
71
Risk assessment can be aided by the use of a decision-tree, which facilitates a logical approach. The way that a decision-tree is used will depend on the operation concerned, e.g. production, packaging, reprocessing, storage or distribution. The best use of QRM tools is discussed further in section 5.
Normally, potential risks in relation to the following should be considered:
■ materials and ingredients;
■ physical characteristics and composition of the product;
■ processing procedures;
■ microbial limits, where applicable;
■ premises;
■ equipment;
■ packaging;
■ sanitation and hygiene;
■ personnel (human error);
■ utilities;
■ supply chain.

The output of a risk assessment is either a quantitative estimate of risk (numeric probability) or a qualitative description of a range of risk (e.g. high/ medium/low) and may be related to a risk matrix (see section 5). The scoring system and trigger points for mitigating action are subjective so the rationale for score categorization should be defined in as much detail as possible. If the score and trigger action are supported by factual evidence it should be more obvious what mitigating action is required – the mitigating action is as important as the score assigned. Professional judgement should be used in interpreting the factual evidence but must be subject to justification.
Records of risk assessments should be maintained.
The expectation of QRM is to assess risks to the product quality and to the patient and then manage these risks so that they are kept at an acceptable level. It is appropriate for companies to assess their control systems so as to implement the appropriate controls to ensure product quality and patient safety. An important principle in QRM is to design risks out of the process or eliminate such risks prospectively, whenever practical and feasible. Risk assessment and mitigation to achieve cost savings, but which could be to the detriment of the well-being of the patient, is an unacceptable practice (9).
3.5 Risk control
Risk control is a decision-making activity designed to reduce and/or accept risks. It usually occurs after risk assessment, and at a fundamental level its purpose is to reduce the risk to an acceptable level.
During risk control activities the following key questions should be asked:
■ What can be done to reduce or eliminate risks?
■ What is the appropriate balance between benefits, risks and resources?
■ Are new risks introduced as a result of the identified risks being controlled?

Risk control can include:
■ not proceeding with the risky activity;
■ taking the risk;
■ removing the risk source;
■ changing the likelihood of the risk;
■ changing the consequences of the risk;
■ sharing the risk with another party (e.g. contractor);
■ retaining the risk by informed decision.

Risk control activities usually involve identifying controls and measures which may reduce or control the risk associated with a failure mode or negative event. Risk control activities can serve to determine critical process parameters for certain controls, how they will be monitored, and the level of qualification and validation, if any, which may be required for such controls.
If risk assessments are conducted and risk controls are employed they should be documented. If the risk assessment is conducted for an ongoing activity it should be subject to periodic review and the frequency of review should be appropriate for the nature of the activity.
Based on the criticality or level of risk, specific corrective actions should be developed to prevent recurrence of instances where there have been deviations from established risk control measures, especially for high risks. These actions should ensure that the risk is brought under control as soon as possible in compliance with the established deviation handling procedures.
Specific corrective actions should be developed in advance for each identified risk, including what is to be done when a deviation occurs and who is responsible for implementing the corrective actions. A record should be kept and maintained of the actions taken.
3.6 Risk review
Appropriate systems should be in place to ensure that the output of the QRM process is periodically monitored and reviewed, as appropriate, to assess new information that may impact on the original QRM decision. Examples of such
73
changes include changes to control systems, changes to equipment and processes,
changes in suppliers or contractors and organizational restructuring. Monitoring is the scheduled measurement or observation of a specific risk
control measure relative to its acceptance limits. Monitoring should be recorded.
All records and documents associated with risk review should be signed
and dated by the person(s) carrying out the review and by a responsible official(s)
of the quality unit of the company.
3.7 Verification of QRM process and methodologies
Once in production, the QRM documentation can be integrated into the quality system and used to provide input into the product process.
The established QRM process and methodologies need to be verified. Verification and auditing methods, procedures and tests, including random sampling and analysis, can be used to determine whether the QRM process is working appropriately. The frequency of verification should be sufficient to confirm the proper functioning of the QRM process.
Verification activities include:
■ review of the QRM process and its records;
■ review of deviations and product dispositions (management control);
■ confirmation that identified risks are being kept under control.

Initial verification of the planned QRM activities is necessary to determine whether they are scientifically and technically sound, that all risks have been identified and that, if the QRM activities are properly completed, the risks will be effectively controlled.
Information reviewed to verify the QRM process should include:
■ expert advice and scientific studies;
■ in-plant observations, measurements and evaluations.

Subsequent verifications should be performed and documented by a QRM team or an independent expert, as needed. For example, verifications may be conducted when there is an unexplained system failure, when a significant change in product, process or packaging occurs or new risks are recognized. Where possible, verification should include actions to confirm the efficacy of all elements of the QRM activities.
In addition, a comprehensive review of the QRM process and specific instances of QRM application by an independent third party may be useful. This would include a technical evaluation of the risk analysis and each element of the QRM process and its application as well as an on-site review of all flow diagrams and appropriate records of the operation of the QRM activity. Such a comprehensive verification is independent of other verification procedures and should be performed to ensure that the QRM process is resulting in the control of the risks. If the results of the comprehensive verification identify deficiencies, the QRM process should be modified as necessary.
Individuals doing verification should have appropriate technical expertise to perform this function.
3.8 Risk communication and documentation
Communication of the QRM process should include key stakeholders. Engaging the key stakeholders in both the data collection process for the risk assessment and the decision-making for risk control will ensure their commitment and support for the QRM. The output of the QRM process and associated risk analysis justifying the approach taken should be documented and endorsed by the organization’s quality unit and management. Additionally, this information should be communicated to stakeholders to keep them informed and to ensure their support.
There should be a report for every risk assessment, but the level of effort, formality and documentation necessary will be commensurate with the level of risk (2).
Regarding conclusions of a risk assessment, the mitigation controls should minimize the likelihood of risk to patient safety to an acceptable level of assurance, on the understanding that no risk whatsoever is unlikely in reality. The degree of risk tolerated very much depends on the circumstances, the proximity to the patient and other controls that might follow in response to the process being assessed before the product reaches the patient (2). It is expected that risk mitigation plans will be developed and implemented wherever any risk to patient safety is posed. Companies should take the holistic view and be mindful that critical issues often arise where multiple failures in systems occur together, so mitigation plans should be sufficiently robust to cover this scenario. Inspectors will assess whether risk assessments underrate the likelihood of occurrence and the consequences of overrating detection such that the patient risk is underestimated. The factual evidence behind statements should be robust to challenge by inspectors.
All risk assessments performed by an organization should be documented. The documentation should list and track all key risks as perceived by the organization and summarize how the risks have been mitigated. There should be a clear reference to risk assessments and a list of risk assessments conducted should be maintained. A management process should be in place to review QRM
– this may be incorporated into the quality management review process.
75
4. QRM application for pharmaceuticals
Training and education
Training of relevant personnel in industry, MRAs and universities in QRM principles and applications is essential for its effective implementation. Industry employees should understand what QRM is, possess the skills necessary to apply it properly, and have access to appropriate resources to enable the effective practice of the QRM principles.
In developing the training programme to support QRM activities, working instructions and procedures should be drawn up which clarify the strategy and define the tasks of all personnel involved in these activities. Specific training should be provided as required to enhance awareness. Staff with the responsibility for managing and reviewing risks should receive formal training in the relevant procedures.
Cooperation between producers, traders and responsible authorities is vital. Opportunities should be provided for the joint training of industrial staff and MRAs to encourage and maintain a continuous dialogue and create a climate of understanding in the practical application of QRM.
The success of QRM depends on the education and training of
management and employees to understand the importance of QRM in producing
and supplying safe pharmaceuticals.
4.2 Responsibilities
Successful application of QRM is dependent on a clear understanding of responsibilities by all personnel involved in the QRM activities. It is recommended that a cross-functional matrix of assigned responsibilities and accountabilities is drawn up and shared with all relevant personnel.
The pharmaceutical manufacturer should ensure that appropriate knowledge and expertise are available for the effective planning and completion of QRM activities. QRM activities are usually, but not always, undertaken by a matrix of interdisciplinary teams. When teams are formed they should include experts from the appropriate areas (e.g. quality unit, product development, engineering, regulatory affairs, production operations, statistics, clinical, and others, such as sales, marketing or legal, as applicable), in addition to individuals who are knowledgeable about the QRM process.
In this respect it is acceptable for external consultants to participate in the QRM matrix team where they can provide specific expertise or knowledge. Their role should be justifiable and clearly defined and the resultant accountability must be understood. A technical agreement or other equivalent document with the consultant may be appropriate where a GMP responsibility is assumed.
Similarly, contract staff may become involved in leading or participating in risk assessments, e.g. a contract authorized person. The extent of their involvement and responsibility and accountability must be documented in a technical agreement or other equivalent document between the individual concerned and the pharmaceutical company. Regarding the authorized person it is important that a company’s internal procedures are clear on where the responsibility lies for final approval of risk acceptance documents.
Effective matrix team leadership is required to take responsibility for coordinating QRM across various functions and departments of the organization and to ensure that the QRM activities are adequately defined, planned, resourced, deployed and reviewed. The leader and team will need to identify critical resources required to implement the QRM activities, and also specify a timeline, deliverables and appropriate levels of decision-making for the QRM process.
4.3 QRM application during product development
The application of QRM procedures evolves through the various stages in the development of a product.
The first QRM exercise should be performed once the QTPP is defined and preformulation work on the candidate medicine is complete. At this stage of a project there may be significant gaps in knowledge. Therefore, it will be important to apply risk tools that are appropriate for such a situation. These might include:
■ cause and effect diagrams (also known as Ishikawa or Fishbone diagrams);
■ flowcharts (e.g. input-process-output (IPO));
■ decision-trees;
■ fault-tree analysis;
■ relationship matrices.

As the product progresses to later stage of development, a more detailed analysis of the risks associated with both the active pharmaceutical ingredient (API) and the FPP should be considered. Risks would cover concerns associated with stability, bioavailability and patient safety including any challenges to these areas resulting from the manufacturing process (including, for example, API form conversion under certain conditions of processing).
As product knowledge advances, more detailed QRM exercises can be considered, concentrating on areas considered to present higher priority risk. As the product's critical quality attributes (CQAs) become defined, the potential risks arising from each input material (API, excipients, any device or pack components) and each secondary product unit operation can be investigated.
77
Eventually, for the developed FPP, the increasingly comprehensive risk
assessment will support a thorough understanding of the product and will enable
all key variables to be identified, understood and controlled.
QRM application during validation and qualification
In keeping with the principles of QRM, these guidelines recommend that process validation embraces the product life-cycle concept already mentioned. Accordingly, process validation activities should involve the generation and evaluation of data throughout the process, from development to full-scale production, which will provide a science-based assurance of consistent delivery of quality product in the production operation (9–10).
It is important to emphasize that the building of scientific assurance begins early in development. It is obtained through rational design of experiments and robust evaluation of data during product and process development through to the commercial production phase, by which time the API and FPP CQAs are well understood and controlled. In this scenario, validation or (perhaps more appropriately termed) conformance batches serve to reinforce the science- or risk-based decisions that have been made as product development has advanced and should demonstrate good control of all critical sources of variability that have been identified. Any unplanned variations within a batch or between batches should be evaluated employing suitable statistical tools, e.g. trend analysis, to check on process control.
A potential advantage of this approach is that there can be flexibility in the number of validation or conformance batches required for regulatory scrutiny prior to approval. The traditional number of batches required for validation has been three but, with QRM embedded in a product's development process, the number of conformance batches needed depends on the depth of knowledge about the process. For very low-volume products, e.g. orphan drugs, this may preclude the need to manufacture multiple batches. It would be beneficial for decisions of this nature regarding conformance batches to have an effective company–MRA dialogue to agree on requirements for a regulatory submission.
When applicable, the principles of QRM should also be applied for qualification activities.
QRM principles can be used to determine the scope of qualification. They
can also be used to determine the optimal schedule for maintenance, monitoring,
calibration and requalification.
Manufacturers should have sufficient knowledge of the process and
product to ensure that by the time the product is commercialized, processes are
optimized and risks are minimized.
4.5 QRM application during commercial manufacturing
In general, implementing QRM should not obviate a manufacturer’s obligation to comply with regulatory expectations (e.g. regulatory requirements, regulatory filings and inspection commitments). All QRM activities should be structured in a way that allows responsibility for risk assessment and actions at appropriate levels of the hierarchy within the organization. Special focus can be put on the risk assessment and risk control during the life-cycle of a product, and may include:
■ product quality risks;
■ adverse impact on patient health resulting from product quality defects;
■ interruption of product supply to patients;
■ GMP and regulatory compliance risks;
■ multisite risks;
■ multiproduct risks;
■ new facility and changes to existing facility, e.g. start-ups, new commercial manufacturing processes, technology transfers and product discontinuation.

After completion of the risk assessment and risk control activities, the outcomes should be summarized and appropriately communicated. The results may be documented in a new or existing report or they may be included as part of another document approved by appropriate decision-makers (e.g. site or functional management, system owner, or quality unit). A risk review is important if new risks or changes to existing risk levels are identified as a result of planned or unplanned events such as routine operation, changes, complaints, product returns, discrepancies or deviations, data monitoring, trends, inspections or audits, or changes in regulatory environment. Risk review may also include evaluation of, for example:
■ effectiveness of risk control activities and actions;
■ changes in observed risk levels or existing controls.

In principal, areas of focus when implementing QRM in commercial manufacturing include a system focus, a process focus and a product focus.
4.5.1 QRM integration with key quality system elements
Effective QRM can facilitate the decision on “What to do?” and, therefore, support better and more informed decisions. QRM should be integrated into existing quality system elements and related business processes and documented appropriately.
79
Accordingly, the use of QRM can be beneficial across a broad spectrum of operations, e.g.:
■ integrated quality management:
?        documentation
?        training and education
?        quality defects
?        auditing and inspection
?        change management and change control (includes equipment, facilities, utilities, control and IT systems)
?        continual improvement and corrective and preventive actions (CAPA);
?        ■ facilities, equipment and utilities:
?        design
?        qualification
?        maintenance and decommissioning of facility or equipment
?        hygiene aspects
?        cleaning of equipment and environmental control
?        calibration and preventive maintenance
?        computer systems and computer-controlled equipment;
?        ■ supplier, materials and contract service management:
?        assessment and evaluation of suppliers and contract manufacturers
?        starting material
?        use of materials –storage
?        logistics and distribution conditions;
?        ■ technology transfer:
?        from development to manufacturing
?        during commercial manufacturing between sites
?        from commercial manufacturing to product discontinuation.

4.5.2 QRM application in product manufacturing operations
Effective QRM can facilitate the “How to do it?” and, therefore, ensure that the products will meet acceptable standards for safety, quality, and compliance.
Among others, QRM methodology can support the following actions to assess and control quality risks:
■ production:
?        manufacturing process risks
?        validation
?        in-process sampling and testing controls
?        production planning
?        deviation and investigation management
?        change management;
?        ■ laboratory control and stability studies:

– out-of-specification results
?        retest period and expiry date
?        method transfers;

■ packaging and labelling:
?        design of packages
?        selection of container-closure system
?        label controls;
?        ■ storage, transport and distribution:

– e.g. cold chain.
5. QRM considerations for medicines regulatory authorities
5.1 Introduction
A key principle of these guidelines is that all MRAs, manufacturing sites in developing countries and API manufacturers should demonstrate, wherever appropriate, application of QRM throughout the product life-cycle for development and manufacturing facilities. Inspectors will review this QRM system as part of the quality systems section of the inspection (along with complaints, recalls, deviations, product quality reviews and others).
Equally, it is recommended that QRM be applied by the MRAs (for examples see (2, 8)) themselves (reviewers and inspectorates) as there are clear benefits of a QRM-based review and inspection plan. For example, inspectors can allocate time and resources commensurate with the perceived significance of
81
risk in any given situation and can be pragmatic regarding the level of scrutiny and degree of formality required.
QRM application to inspection strategy
5.2.1 Risk management in inspections
The inspection section or unit of an MRA should operate within a written, implemented quality management system (11). SOPs should be followed for activities including (but not limited to) inspection planning, review of corrective and preventive actions after inspections and complaint handling and investigation. Where appropriate, the procedures and activities during inspection should be in line with the principles of QRM.
The unit should have a risk management plan that describes the philosophy, approach, procedures and implementation of risk management. The risk management plan should be reviewed and updated on a continuous basis, or at least annually, and should cover all types of inspections (including GMP, good clinical practices (GCP), good laboratory practices (GLP)) and other activities.
Appropriate risk assessment tools should be used in the process, and
the risk assessment for a site to be inspected should be documented on a risk
assessment worksheet. Records should be maintained.
A metric system should be used for risk ratings, e.g. on a scale from 1 to 3.
5.2.2 Inspection planning and conduct
The frequency and scope of inspections should be determined based on risk assessment that covers product risk and patient risk.
Risk rating should normally be done only for sites that have been previously inspected. The risk assessment worksheet should be completed after every inspection. Inspection of a site that has not been inspected previously may be waived only in cases where a recognition procedure exists between regulatory inspection units, and where, in addition, appropriate evidence of GXP compliance is available which indicates that there is no risk or an acceptably low risk to products and patients.
Various factors should be considered in the risk assessment exercise, and
these factors may be different for the different types of GXP inspections. Risk
factors to be considered depend on the type of inspection, and may include:
■ outcome of inspection by another regulatory authority;
■ outcome of the previous inspection;
■ complexity of the site (e.g. buildings, utilities);
■ complexity of the product (e.g. sterile, non-sterile);
■ type of product (e.g. biological, low-dose);
■ complaints and recalls;
■ significance of changes (e.g. equipment, key personnel);
■ results of product testing;
■ risk to the patient;
■ complex route of synthesis (API);
■ polymorphism (API);
■ biopharmaceutical classification of the product;
■ innovative or emerging technology.

The number of inspectors and number of days required for the inspection, as well as the scope of the inspection, should be determined based on the risk rating of the site inspection.
Inspection reports should contain findings and observations. Departures from GXP should be classified where appropriate, as “critical”, “major” or “minor”.
The unit should have an SOP that describes the classification process. Classification should be based on risk assessment. The level of risk assigned should be in accordance with the nature of the observation as well as the number of occurrences.
5.2.3 Corrective action and preventive action review, and scheduling of routine inspections
CAPA should be requested from a site, following an inspection. The CAPAs should address the observations included in an inspection report. Based on the outcome of the inspection and the acceptability of the CAPA, the risk rating of the site should be reviewed and recorded.
Inspection frequency should be defined based on the risk rating. For example, the frequency can be defined as every 6, 12, 18 or 24 months. (Note: The maximum time interval should be no more than every 36 months.)
5.2.4 Complaint handling and investigation
Handling and investigation of quality complaints should be done in accordance with a written SOP. The scope and depth of the investigation (including whether a desk review or on-site inspection will be done) should be based on risk assessment.
5.3 Inspection of QRM at a manufacturing site
Note: During inspections, inspectors should assess whether a manufacturer has appropriate skills and scientific knowledge, as well as product and process knowledge, for the QRM procedure being inspected. This is also relevant where a company has made use of contracted parties.
83
The company's QRM procedure should be appropriately detailed and
should be integrated into the company’s quality management system. It should
cover at least the following areas:
■ It should specify the general approach to both planned and unplanned risk assessment, including scope, responsibilities, controls, approvals, management systems, applicability and exclusions.
■ Personnel should have appropriate qualifications, experience and training. Their responsibilities with regard to QRM should be clearly defined.
■ Senior management should be involved in the identification and implementation of QRM principles within the company.
■ The risk management procedure(s) for each area of application should be clearly defined.
■ Quality assurance principles should be applied to QRM-related documentation, e.g. review, approval, implementation and archiving.

QRM policies and procedures should be clear and the workflow should be systematic and conducted in a logical order.
■ The procedure for risk management should be implemented.
■ Manufacturers should identify significant risks and consider all the relevant data from reliable sources.
■ The level of effort and resources used in risk assessment should be appropriate to the importance of the identified problem.
■ Critical issues should be addressed with appropriate urgency and formality.
■ There should be a logical selection of tools for risk assessment.
■ Risk acceptance criteria should be appropriate.
■ Risk assessments should not underrate the severity, nor overrate detection of occurrences resulting in underestimating patient risk.
■ The risk acceptance criteria should be appropriate for the specific situation in question.
■ Risk controls should be effective.
■ The company should have a review programme to measure the effectiveness of the measures taken.
■ Risk-based decision(s) should be science-based and concordant with the predefined acceptance criteria.

All documentation related to the QRM activities should be completed within a reasonable period and should be accessible. Risk assessments performed should be reviewed when appropriate, and additional controls implemented when required.
Personnel should be trained and assessed in the principles of QRM. Where appropriate, a team of members of personnel should participate in the QRM processes.
5.4 QRM applied to dossier review (assessment)
The assessment processes of national medicines regulatory authorities (NMRAs) rely on QRM principles in the management of resources (time and assessors), as well as in the management of product-related risk factors. Efficient management of resources minimizes the risk that limited resources are not used to their best effect, and ultimately ensures that important products are made available in a timely manner. Key factors to be considered include the prioritization of dossiers, the screening process, identification of the specific risk factors inherent to a given dossier or dosage form, and allocation of resources to the various sections of a dossier for a given product. In addition, product-related risk factors must be managed throughout the life-cycle of the product, for example, through effective communication between assessors and inspectors, and by establishing systems for dealing with the products after approval.
The allocation of priority to dossiers should take into account the therapeutic needs of the regional population (e.g. disease occurrence, the need for paediatric formulations, combination products, or experience with innovative or emerging technology) and the availability of medicines on the market. Prioritization should be a dynamic process to enable it to accommodate emerging issues such as pandemics. Other considerations related to prioritization based on medical need may include fixed-dose combinations versus single-ingredient or co-packaged products, extended release products versus products administered as two or three daily doses, second-line versus first-line products, flexible dosage forms such as dispersible tablets and variable dose products such as oral liquids.
The screening process examines the completeness of a dossier. Screening ensures that only those dossiers that meet minimum standards for completeness can enter into the full assessment process. Insufficient screening processes allow lower quality dossiers to be accepted for review, thus significantly increasing assessment time.
Identification of dossier-related and product-related risk factors allows for the allocation of appropriate resources to specific dossiers. Possible risk factors include: the experience and track record of the manufacturer, narrow therapeutic range products, sterile versus non-sterile APIs and products;
85
API-related considerations such as use of semi-synthetic and fermentation products, complex routes of synthesis, polymorphism, isomerism and potential genotoxic impurities; and product-related considerations such as the use of novel excipients, the complexity of the formulation, single-ingredient versus fixed-dose combinations, and special delivery systems (e.g. modified release, transdermal products, and inhalation products). Once risk factors have been identified, resources should be allocated to minimize risk. For example, assessors with expertise related to the product-related risk identified should be assigned to assess the dossier whenever possible. When resources allow, the assessors may be organized according to specialization, assigning assessors to various product categories (e.g. generic products, sterile products, solid oral dosage forms, or special delivery systems). This can facilitate the development of expertise in key areas and promote consistency of review, as well as ensuring that products requiring specialized knowledge are identified and assessed by those with the appropriate expertise. Where a high level of risk is identified for a dossier, the more experienced assessors need at least to be available on a consultation basis.
The risk level associated with a dossier may change during the course of assessment. For example, rejection of the bioequivalence study will result in additional time required to conduct and assess additional studies and associated additional quality information. In such a scenario the risk relates both to the use of additional resources and to an increased risk that the overall product quality may be poor.
Allocation of resources to various aspects or sections of the dossier is an important QRM consideration, in order to ensure that the resources used are commensurate with the risk level. An understanding of the relative criticality of dossier sections or aspects is necessary for efficient use of resources. All aspects of the dossier are important to achieve overall quality, safety and efficacy; however some areas are inherently more critical from a risk perspective and warrant more attention in the assessment process. Examples include the clinical reviews, bioavailability reviews, API synthesis, specifications and stability studies, FPP manufacturing details, pharmaceutical development studies including biowaiver justification, process validation, specifications and stability studies. An example applicable to most simple solid oral products is that more time should be allocated to the review of manufacturing steps prior to packaging than to reviewing the packaging process.
During the assessment process there should be a standard procedure for communicating to the inspectors those issues identified which may require consideration during inspection. After approval of a product, QRM principles should be applied to evaluate the impact of proposed variations or changes. Clear guidelines that outline possible post-approval changes and assign an associated risk level are an effective means to achieve this.
6. Risk management tools
A variety of tools can be used for the purposes of QRM, either alone or in combination. It is important to note that no single tool or combination of tools is applicable to every situation in which a QRM procedure is used. Examples of tools are listed in regulatory guidance (6, 8); neither list is exhaustive. The important criterion for acceptability is that the tool or tools are used effectively to support the key attributes of a good risk assessment.
The Product Quality Research Institute (PQRI) Manufacturing Technology Committee (MTC) has produced a summary (9) of common risk management principles and best practices, several working tools to foster consistency in the use of ICH Q9 (5) in day-to-day risk management decision-making, and a series of examples of risk management applications currently in use by major pharmaceutical firms. They have also produced very helpful risk tool training modules for risk ranking and filtering, failure modes effects analysis (FMEA) (12–15), hazard operability analysis (HAZOP) (16) and HACCP (3).
One aspect worth highlighting is the development of a risk matrix to facilitate categorization of risks identified during the risk assessment phase. In order to prioritize a risk, it is essential to agree upon its significance. The risk associated with any situation or event can be represented as the impact of that event multiplied by the probability of its occurrence; in other words: how likely is it to happen? and how severe would it be if it did happen? Impact and probability can each be classified, e.g. into 5 levels (1–5) or with a weighting towards the higher probability and impact ratings (e.g. 1, 3, 5, 7, 10, etc.), so that a grid or matrix can be constructed (Table 1).
Table 1
An example of a probability versus impact matrix
Impact
Probability Negligible Marginal Moderate Critical Catastrophic

The shading in the table represents an example of how the risk values (sometimes called composite risk indices or risk index values) can be assigned a high, medium or low status. The definition for each status should be predetermined in the QRM process after consideration of the specific consequences for the process undergoing risk assessment. These consequences can be split according to the probability and impact scores, as exemplified in Table 2.
Table 2
Example of a consequences table for probability and impact

WHO Technical Report Series No. 981, 2013
MRA, Medicines regulatory authority. Source: Based on reference 9. This table has been amended, but was originally produced within the context of the Product Quality Research Institute (PQRI), 2107 Wilson Blvd, Suite 700, Arlington, Virginia
__________
_64"__XFC_TJUF__IUUQ___XXX_QRSJ_PSH_JOEFY_BTQ__123*_IBT_LJOEMZ_BHSFFE_UP_UIF_VTF_PG_JUT_
material.
This table is a very basic example and would need to be customized for the specific process in question to enable a better and more practical definition of the consequence categories. It should be cautioned that the value of a risk matrix relies very heavily upon input information and should only be used by staff with a good understanding of the embedded judgements and, as such, the resolution of the low, medium or high categorization.
As a summary of the common, well-recognized QRM tool options available for the purposes of these guidelines, Table 3 has been based on the one from the Product Quality Research Institute Manufacturing Technology Committee (PQRI-MTC) report (9). The list is not comprehensive but it does include some of the more frequently used approaches.
Table 3
Examples of common risk management tools
Risk management tool Description, attributes Potential applications




continues
Table 3 continued
Risk management tool Description, attributes Potential applications

Hazard operability analysis (HAZOP)

t_Better for preventive applications than reactive
t_Valuable precursor or complement to process validation
t_Assessment of the efficacy of critical control points and the ability to consistently execute them for any process
'BJMVSF_NPEFT_FõFDUT_ BOBMZTJT_'.&"
t_Tool assumes that risk events are caused by deviations from the design and operating intentions
t_Uses a systematic
UFDIOJRVF_UP_IFMQ_JEFOUJGZ_
potential deviations from normal use or design intentions
t_Assumes comprehensive understanding of the process and that CPPs have been defined prior to initiating the assessment. Tool ensures that CPPs will be met.
t_Assesses potential failure modes for processes, and UIF_QSPCBCMF_FõFDU_PO_ outcomes and/or product performance
t_Once failure modes are known, risk reduction actions can be applied to eliminate, reduce or control potential failures
t_Access manufacturing processes, suppliers,
GBDJMJUJFT_BOE_FRVJQNFOU
t_Commonly used to evaluate process safety hazards
t_&WBMVBUF_FRVJQNFOU_
and facilities; analyse a manufacturing process to identify high risk steps and/or critical parameters
continues
Table 3 continued
Risk management tool Description, attributes Potential applications


Source: Based on reference 9. This table has been amended, but was originally produced within the context of the Product Quality Research Institute (PQRI), 2107 Wilson Blvd, Suite 700, Arlington, Virginia
__________
_64"__XFC_TJUF__IUUQ___XXX_QRSJ_PSH_JOEFY_BTQ__123*_IBT_LJOEMZ_BHSFFE_UP_UIF_VTF_PG_JUT_
material.
References
1. Quality assurance of pharmaceuticals. A compendium of guidelines and related materials. Vol. 2, 2nd updated ed. Good manufacturing practices and inspection. Geneva, World Health Organization, 2007; Quality assurance of pharmaceuticals. A compendium of guidelines and related materials. World Health Organization, 2011 (CD-ROM) (http://www.who.int/medicines/areas/quality_safety/ quality_assurance/guidelines/en/index.html).
2. EudraLex The rules governing medicinal products in the European Union, Vol. 4. Good manufacturing practice (GMP) guidelines (http://ec.europa.eu/health/documents/eudralex/vol-4/index_en.htm).
3. Application of hazard analysis and critical control point (HACCP) methodology to pharmaceuticals. In: Quality assurance of pharmaceuticals. A compendium of guidelines and related materials. Vol. 2, 2nd updated ed. Good manufacturing practices and inspection. Geneva, World Health Organization, 2007; Quality assurance of pharmaceuticals. A compendium of guidelines and related materials. World Health Organization, 2011 (CD-ROM) (http://www.who.int/medicines/areas/quality_safety/ quality_assurance/guidelines/en/index.html).
4. ICH harmonised tripartite guideline. ICH Q8(R2): Pharmaceutical development. August 2008 (http://www.ich.org).
5. ICH harmonised tripartite guideline. ICH Q9: Quality risk management 9 November 2005 IFPMA; Quality Risk Management ICH Q9 Briefing pack, July 2006, ICH-webpage publishing; ICH harmonised Q8/9/10 Questions & Answers, November 2010; ICH harmonised Q8/9/10 Training material, November 2010, ICH-webpage publishing; ICH harmonised points to consider for ICH Q8/Q9/Q10 implementation, 6 December 2011 (FIP, AM and IFPMA) (http://www.ich.org).
6. Guidance for industry: PAT – A framework for innovative pharmaceutical development, manufacturing and quality assurance. US Food and Drug Administration, Center for Drug Evaluation and Research (FDA CDER), September 2004 (http://www.fda.gov/Drugs/default.htm).
7. Pharmaceutical cGMPs for the 21st century – A risk-based approach. US Food and Drug Administration, Center for Drug Evaluation and Research (FDA CDER), September 2004 (http:// www.fda.gov/Drugs/default.htm).
8. Medicines and Healthcare Products Regulatory Agency. MHRA guidance: GMP-QRM – Frequently
asked questions (http://www.mhra.gov.uk/Howweregu ... ectionandstandards/ GoodManufacturingPractice/FAQ/QualityRiskManagement/index.htm).
9. Frank T et al. Quality risk management principles and industry case studies (December 2008) sponsored by the Product Quality Research Institute Manufacturing Technology Committee (PQRI-MTC) (http://www.pqri.org).
10. Boedecker B. GMP Inspectorate of Hannover,  Germany. EU GMP requirements – quality systems. Presentation Ankara, Turkey Ministry of Health, 20–21 October 2009.
11. WHO guidelines on quality system requirements for national good manufacturing practice inspectorates. In:  WHO Expert Committee on Specifications for Pharmaceutical Preparations. Thirty-sixth Report. Geneva, World Health Organization, 2002 (WHO Technical Report Series, No. 902), Annex 8 (http://www.who.int/medicines/are ... nce/inspections/en/ index.html).
12. US Department of Health and Human Services Food and Drug Administration Center for Drug Evaluation and Research (CDER)/Center for Biologics Evaluation and Research (CBER)/Center for Veterinary Medicine (CVM) guidance for industry – process validation: general principles and practices. Silver Spring, MD, IFPMA, 2011 (http://www.fda.gov/downloads/Drugs/ GuidanceComplianceRegulatoryInformation/Guidances/UCM070336.pdf).
13. Stamatis DH. Failure mode and effect analysis. FMEA from theory to execution, 2nd ed. Milwaukee, American Society for Quality, Quality Press, 2003.
14. Guidelines for failure modes and effects analysis (FMEA) for medical devices. Ontario, Canada, Dyadem Press, 2003.
15. McDermott R et al. The basics of FMEA. Portland, OR, Productivity, 1996.
16. IEC 61882 - Hazard operability analysis (HAZOP). Geneva, International Electrotechnical Commission, Headquarters (IEC 61882 Ed.1, b:2001).

Further reading
FDA's new process validation guidance – A detailed analysis. European Compliance Academy, November
2008 (http://www.gmp-compliance.org/eca_news_1402_5699,6013.html). Validation of analytical procedures used in the examination of pharmaceutical materials. In: WHO Expert Committee on Specifications for Pharmaceutical Preparations. Thirty-second report. Geneva, World Health Organization, 1992 (WHO Technical Report Series, No. 823), Annex 5 (http://who.int/medicines/ publications/pharmprep/en/index.html).
回复

使用道具 举报

宗师
 楼主| 发表于 2013-6-29 09:00:21 | 显示全部楼层


附件2

WHO guidelines on quality risk management

谁对质量风险管理指引

1. Introduction

1。景区简介

1.1 Background and scope 62

1.1背景和范围62

1.2 Principles of quality risk management 64

质量风险管理的原则64 1.2

2. Glossary 67

2。表67

3. Quality risk management process 70

3。质量风险管理过程70

3.1 Initiating a QRM process 70

3.1启动质量风险管理过程70

3.2 Personnel involved in QRM 70

3.2的人员参与质量管理70

3.3 Knowledge of the product and process 71

3.3了解产品和过程71

3.4 Risk assessment 71

3.4风险评估71

3.5 Risk control 72

3.5风险控制72

3.6 Risk review 73

3.6风险审查73

3.7 Verification of QRM process and methodologies 74

3.7验证fi阳离子质量风险管理的步骤和方法74

3.8 Risk communication and documentation 75

3.8风险沟通和文档75

4. QRM application for pharmaceuticals 76

4。质量风险管理的应用药物76

4.1 Training and education 76

4.1培训和教育76

4.2 Responsibilities 76

4.2职责76

4.3 QRM application during product development 77

4.3质量管理应用产品开发中的77

4.4 QRM application during validation and qualification 78

4.4质量风险管理的应用中验证和质量fi阳离子78

4.5 QRM application during commercial manufacturing 79

商业制造的79在4.5质量风险管理中的应用

4.5.1 QRM integration with key quality system elements 79

4.5.1 QRM结合关键质量体系要素79

4.5.2 QRM application in product manufacturing operations 80

4.5.2质量风险管理的应用在产品的制造业务,80

5. QRM considerations for medicines regulatory authorities 81

5。药品监管部门81质量风险管理的思考

5.1 Introduction 81

5.1引言81

5.2 QRM application to inspection strategy 82

5.2质量风险管理的应用检验策略82

5.2.1 Risk management in inspections 82

5.2.1风险管理在检查82

5.2.2 Inspection planning and conduct 82

5.2.2检验计划和进行82

5.2.3 Corrective action and preventive action review, and scheduling of routine inspections 83

5.2.3纠正措施和预防措施的审查,和调度的常规检查83

5.2.4 Complaint handling and investigation 83

5.2.4投诉及调查83

5.3 Inspection of QRM at a manufacturing site 83

在制造现场83 5.3检验质量风险管理

5.4 QRM applied to dossier review (assessment) 85

5.4质量管理应用到档案的回顾(评价)85

6. Risk management tools 87 References 91

6。风险管理工具,参考文献87篇91
清空内容
回复

使用道具 举报

宗师
 楼主| 发表于 2013-6-29 09:02:39 | 显示全部楼层
大多数国家的良好生产规范(GMP)规(1,2)(包括验证),药品监管活动和检查,结合供应链控制整个产品生命周期,提供了良好的保障,风险是很大程度上控制。然而,在控制是不太有效,患者可能会在风险通过质量不合格的药品生产。个体风险的具体产品和原料,在生产或分配特定阶段的风险识别与评估应允许监管部门通过增加内的可用资源的限制其活动的有效性提高控制药物。质量风险管理(风险管理)是一个过程,是所有国家有关,应该理解风险和减轻它通过适当的和强大的控制提供了理论基础。

The aim of these guidelines is to assist the development and implementation of effective QRM, covering activities such as research and development, sourcing of materials, manufacturing, packaging, testing, storage and distribution. In the past, hazard analysis and critical control point (HACCP) methodology, traditionally a food safety management system but subsequently applied to other industries, has been the basis of WHO risk management guidance to the pharmaceutical industry (3).

这些准则的目的是协助有效的质量风险管理的发展与实施等活动,包括研究和开发,采购,制造,试验,包装,储存和分配。在过去,危害分析与关键控制点(HACCP)的方法,传统的食品安全管理体系,但随后应用于其他行业,一直是一个风险管理指导,制药行业的基础(3)。

More recently international guidance has emerged (2, 4–7) that is of specific relevance to the pharmaceutical industry and which addresses the full scope of pharmaceutical industry QRM more effectively than HACCP principles, including how to structure regulatory filings using a risk-based approach. Consequently, these WHO guidelines have been developed as an update on WHO's advice to the pharmaceutical industry, taking account of this new guidance.

最近国际指导已经出现(2,4–7),医药行业的具体关联和解决医药行业QRM全范围比HACCP原则更有效,包括如何结构的监管文件中使用基于风险的方法。因此,这些谁已开发的指导方针,作为更新谁给医药行业的建议,以指导这个新帐户。

To protect patients in terms of quality, safety and efficacy of medicines, international medicines regulatory authorities (MRAs) are recommending pharmaceutical manufacturers to adopt a risk-based approach to the life-cycle of a pharmaceutical product. Some MRAs require the adoption of a risk-based approach for specific areas in the life-cycle of a pharmaceutical product, e.g. environmental monitoring in sterile products manufacture. The level of QRM activity and the density of associated documentation will evolve as the product progresses from early development through to routine production.

保护在质量的患者,药物安全有效,国际药品监管部门(MRAS)推荐的药品生产企业采用的药物产品的生命周期风险评估的方法。一些方法需要一个基于风险的方法在医药产品的生命周期的特定区域,采用无菌产品,如环境监测制造。质量风险管理活动的水平和相关文件的密度会随着产品的发展从早期开发到日常生产的发展。

QRM is the overall and continuing process of appropriately managing risks to product quality throughout the product's life-cycle in order to optimize its benefit–risk balance. It is a systematic process for the assessment, control, communication and review of risks to the quality of the medicinal product. It can be applied both proactively and retrospectively.

质量风险管理是全面和持续的适当的风险管理产品全程质量为产品的生命周期优化效益–风险平衡过程。这是一个系统的评估,过程控制,对药品的质量风险沟通与回顾。它可以应用于主动和回顾。

While the choice of the tools to support the QRM approach is optional and may vary, the tools chosen need to be appropriate for the intended use.

而选择的工具支持的风险管理方法是可选的,可能会有所不同,所选择的工具需要适合预期用途。

In return for using this approach, there are potential opportunities for both MRAs and pharmaceutical manufacturers (8) as summarized in the following sections.

在使用这种方法返回时,有两个MRAS制造商和制药公司潜在的机会(8)总结在下面的章节。

■ Quality risk management (QRM) principles can be applied to both MRAs and pharmaceutical manufacturers:

■质量风险管理(QRM)原则可以应用到两个MRAS和制药企业:

? MRAs: systematic and structured planning of reviews and inspections that are risk-based. The submission review and inspection programmes can also operate in a coordinated and synergistic manner.

?方法:系统回顾和检查的,以风险为基础的结构规划。提交评审和检查计划,也可以在一个协调的协同运作方式。

? Manufacturers: design, development, manufacture and distribution, i.e. the life-cycle of a pharmaceutical product. QRM should be an integral element of the pharmaceutical quality system (QS).

?制造商:设计,开发,制造和销售,即医药产品的生命周期。质量风险管理是质量体系的一个组成元素(QS)。

? ■ Science-based decision-making can be embedded into QRM processes:

?■科学为基础的决策可以嵌入到质量风险管理过程:

? MRAs: decisions regarding review, inspection or inspection frequency should consider product risk and GMP compliance of the manufacturer. The MRA accepts residual risks through understanding the QRM decisions involved.

?方法:决定审查,检查或检验频率应考虑产品的风险和厂家的GMP合规。MRA接受残余风险通过对质量风险管理决策参与。

? Manufacturers: quality decisions and filing commitments can be based on a science-based understanding of the process and QRM (when using the quality by design approach, and other approaches where appropriate). Its effective application should offer manufacturers greater freedom to decide how to comply with the principles of GMP and this, therefore, should encourage innovation.

?制造商:决定和质量文件的承诺可以基于一个以科学为基础的过程和质量风险管理的认识(当使用质量的设计方法,和其他方法在适当的地方)。它的有效应用,应提供制造商更大的自由来决定如何符合GMP和这一原则,因此,应鼓励创新。
回复

使用道具 举报

药徒
发表于 2013-6-29 09:07:30 | 显示全部楼层
回复

使用道具 举报

宗师
 楼主| 发表于 2013-6-29 09:13:33 | 显示全部楼层
ygfyzy 发表于 2013-6-29 09:07
请以这个为原文组织翻译:WHO guidelines on quality risk management

WHO关于质量风险管理的最终指南发布
https://www.ouryao.com/forum.php? ... 3&fromuid=25184
论坛里有这个
回复

使用道具 举报

药徒
发表于 2013-6-29 09:27:24 | 显示全部楼层
本帖最后由 ygfyzy 于 2013-6-29 09:29 编辑
毒手药王 发表于 2013-6-29 09:13
WHO关于质量风险管理的最终指南发布
https://www.ouryao.com/forum.php?mod=viewthread&tid=144903&fromu ...

不要用你这贴出来的翻译,更不要用机器翻译!
回复

使用道具 举报

宗师
 楼主| 发表于 2013-6-29 09:33:23 | 显示全部楼层
欢迎高手来翻译,
回复

使用道具 举报

药徒
发表于 2013-6-29 09:58:46 | 显示全部楼层
本帖最后由 ygfyzy 于 2013-6-29 10:05 编辑

不能用机器翻译,这应该是翻译过程的原则问题!不知道@毒手药王 是怎么看待的?
看看机器翻译的错误:
QQ截图20130629100523.jpg
回复

使用道具 举报

宗师
 楼主| 发表于 2013-6-29 10:12:24 | 显示全部楼层
ygfyzy 发表于 2013-6-29 09:58
不能用机器翻译,这应该是翻译过程的原则问题!不知道@毒手药王 是怎么看待的?
看看机器翻译的错误:

机器翻译错的挺明显的,但比以前的软件强多了。
回复

使用道具 举报

药徒
发表于 2013-6-29 11:07:08 | 显示全部楼层
省事的方法就是先机器翻译(多几个软件翻译,比较哪个意思更贴切),再手工修改完善!
回复

使用道具 举报

药士
发表于 2013-6-29 11:43:47 | 显示全部楼层
郭家局不是有高人么,他们翻
回复

使用道具 举报

药生
发表于 2013-6-29 11:54:22 | 显示全部楼层
回复

使用道具 举报

药士
发表于 2013-6-29 13:52:11 | 显示全部楼层
用谷歌翻译,基本搞定。。。。。。。。。。。。。哈哈
回复

使用道具 举报

药徒
发表于 2013-7-1 07:54:34 | 显示全部楼层
回复

使用道具 举报

发表于 2013-7-1 19:04:57 | 显示全部楼层
谢谢,顶一下
回复

使用道具 举报

发表于 2013-7-11 09:02:30 | 显示全部楼层
现在还没有能代替人工的翻译软件 。
我觉得发贴之前也要考虑下可行性。我看了下这篇文章将近9700个单词,译成中文差不多15000字。英语水平好的人也要满满5天才能完成,最低费用1200大洋。
这样免费求助不可行呀。用谷歌搞下,做和没做有什么区别。
回复

使用道具 举报

发表于 2013-8-5 09:56:11 | 显示全部楼层
本 地 诚 信 快 速 办 理 证 Q Q 2596305122货 到 满 意 付 款
办 理 范 围 :【Q Q:2596305122】
各 学 校 毕 业 证、高 中、中 专、职 业 学 校、高 等 院 校 学 历 证 书、自 学 考 试、函 授、英 语、计 算 机 等 级 证 书 以 及 各 种 档 案 材 料(含 专 科、本 科、研 究 生、硕 士、博 士 等)。并 可 根 据 客 户 要 求 办 理。【QQ:2596305122】 
电 焊 工 技 术 等 级 证 书、叉 车 证、铲 车 证、部 队 退 伍 证、厨 师 资 格 证、车 船证、导 游 证、各 类  作 证、各 级 教 师 证、房 产 证、 医 师 证、会 计 师、会 计 证、组 织 机 构 代 码 证、 税 务 登 记 证、 建 筑 资 质 证、工 程 师 证、企 业 营 业 执 照,公 路 养 路 证,房 地 产 权 证。本 公 司 能 办理 所 有 的 证 及 公 私 章,其 他 的 请 联 系 客 服!本 公 司 坚 持 合 作 共 赢,互 惠 互 利,一 切 使 客 户 满意,遵 从 服 务 客 户 经 营 理 念,坚 持 薄 利 多 销 原 则,一 次 合 作 终 身 朋 友。
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

×发帖声明
1、本站为技术交流论坛,发帖的内容具有互动属性。您在本站发布的内容:
①在无人回复的情况下,可以通过自助删帖功能随时删除(自助删帖功能关闭期间,可以联系管理员微信:8542508 处理。)
②在有人回复和讨论的情况下,主题帖和回复内容已构成一个不可分割的整体,您将不能直接删除该帖。
2、禁止发布任何涉政、涉黄赌毒及其他违反国家相关法律、法规、及本站版规的内容,详情请参阅《蒲公英论坛总版规》。
3、您在本站发表、转载的任何作品仅代表您个人观点,不代表本站观点。不要盗用有版权要求的作品,转贴请注明来源,否则文责自负。
4、请认真阅读上述条款,您发帖即代表接受上述条款。

QQ|手机版|蒲公英|ouryao|蒲公英 ( 京ICP备14042168号-1 )  增值电信业务经营许可证编号:京B2-20243455  互联网药品信息服务资格证书编号:(京)-非经营性-2024-0033

GMT+8, 2025-6-11 02:41

Powered by Discuz! X3.4

Copyright © 2001-2020, Tencent Cloud.

声明:蒲公英网站所涉及的原创文章、文字内容、视频图片及首发资料,版权归作者及蒲公英网站所有,转载要在显著位置标明来源“蒲公英”;禁止任何形式的商业用途。违反上述声明的,本站及作者将追究法律责任。
快速回复 返回顶部 返回列表