仪表回路检查方案
Loop Check Scheme
1.    编制说明
Edit description
本方案适用于上海工业气体公司合成气装置2期扩建项目仪表工程,包括回路检查的各项规定及相应要求。同时列出回路检查的方法及标准,在回路检查过程主要负责现场模拟信号及接点信号的输入工作,DCS操作站上操作主要由厂家及现场操作人员负责;同时要求有其他相关专业的协调与配合。
This Scheme is apply to Hyco II Instrument Projectof Shanghai Industrial Gas Company, including loop check specifications andrelevant requirements. The loop check method and standard have been listed.During the loop check, we are only responsible the local analog signal andpoint signal input. DCS operating station is mainly responsible by vendor andsite operators; at the same time, it is requested coordinate and cooperate fromother specialties.  
2.    编制依据
Edit basis
GB50093 2002《自动化仪表工程施工及验收规范》
GB50093 2002《Automation Instrument EngineeringConstruction and Acceptance Specifications》
SH3521-2007 《石油化工仪表施工规程》
SH3521-2007Petrochemical Instrument Construction Regulations
SH3503-2007 《石油化工建设工程项目交工技术文件规定》
SH3503-2007Petrochemical Construction Project Hand Over Technical and DocumentRules
GB50168-2006 《电缆线路施工及验收规范》
GB50168-2006Cable Run Construction and Acceptance Specification
SY4031-93 《石油建设工程质量检验评定标准自动化仪表安装工程》
SY4031-93《Petrochemical Engineering Quality Inspection Assessment StandardAutomation Instrument Installation project》
GB50131-2007《自动化仪表工程施工质量验收规范》
GB50131-2007Automation Instrument Project Construction Quality AcceptanceSpecification
SH3543-2007 石油化工建设工程项目施工过程技术文件规定(通用电气仪表)
SH3543-2007 Petrochemical Construction ProjectConstruction Process Technical Document Specification (GeneralElectric/Instrument)
69817-01-0850001 鲁奇规范 《仪表通用规范》
69817-01-0850001 Lurgi SpecificationGeneral Instrument Specification
69817-01-0850071 鲁奇规范 《回路检查工程规定》
69817-01-0850071  Lurgi SpecificationLoop Check Project Specification
3回路检查的一般规定
   Generalprovision on Loop Check
3.1 回路检查应在系统投入运行前进行,试验前系统应具备下列条件:
    Loop checkshould be carried out before the system put into operation, the followingconditions should be available.
3.1.1回路检查文件夹已准备完整,符合规范要求;
    Loop check document folder have been prepared and fulfilledspecification requirements;
3.1.2 回路中的仪表设备、装置和仪表线路、仪表管道应安装完毕;
     Theinstruments, devices and instrument line, instrument pipeline in the loopshould be completely installed;
3.1.3 仪表配线和配管经检查确认正确完整,配件附件齐全;符合试验要求;
     Instrumentwiring and piping should be checked and confirmed completely, fittings and accessoryis complete in accordance with test requirements;
3.1.4 回路中的电源、气源已能正常供给并符合仪表运行的要求;
     Power and gas resource in the loop shouldbe supplied normally and in accordance with operating requirement;
3.1.5气源管道经吹扫、气密性试验合格,已通入压力稳定的仪表空气;
     Air source pipeline has been purged andair test qualified, instrument air with stable pressure has been put into thesystem;
3.1.6电气回路已进行校线及绝缘检查,接线正确、端子牢固、接触良好、标识正确;
     Electric loop has been tested, insulationchecked , wiring correct, terminal fastness, contact in good condition, proper label;
3.2 参加系统试验的施工人员应熟悉图纸及仪表系统工作原理,并具有熟练的调试技术。
    Constructors involve with the system testshould familiar with the drawing and instrument system operating principle andwith skill debugging technical.
3.3 回路检查应根据现场情况和回路的复杂程度,按回路位号和信号类型合理安排,回路试验应做好相应的试验记录;
   Loop check should be reasonably arrangedaccording to site condition and loop complexity level, and loop position numberand signal type. Loop check should be recorded accordingly;
3.4 仪表试验用的标准仪器仪表应具备有效的计量检定合格证,其基本误差的绝对值不超过被校准仪表基本误差绝对值的1/3;
   The standard instrument using in instrumenttest should equipped with measure calibration certification, the absoluteintrinsic error data should not over than 1/3 to the instrument to be tested;
                                                                                                                                                                                                                                                                                                                           
3.5 仪表校试验的条件、项目、方法应符合产品技术文件的规定和设计文件要求;
    The instrument test condition、item、method should be accordance withproduct technical specification and design requirements;
4. 回路检查的方法及要求
   Loop TestMethod and Requirement
4.1 回路检查文件夹的准备:
    Loop check folder prepare:
4.1.1 仪表数据表、回路接线图、Hook-up图;
     Instrumentdata sheet、loop wiring drawing、Kook-updrawing;
4.1.2  Vendor提供的仪表标定数据表及部分阀门的HOOK-UO图;
      Instrument rating data table provided byVendor and part of valve Hook-up drawing;
4.1.3 仪表设备安装检查记录:           
     Instrumentinstallation check report;
4.1.4 模拟量输入回路的试验报;
     Analog quantity input loop test report;
4.1.5 模拟量输出回路试验报告;
     Analog quantity output test report;
4.1.6 仪表导压管/气源管检查(泄漏及气密性检测)报告;
     Instrument guide piping/air source testreport(leakage test and air tightness test );
4.1.7 开关量仪表输入/输出检查,主要检查现场自控阀的动作是否到位、操作站上的反馈信号是否正确;
     Switch value input/output check, to checklocal automation valve act in place or not、feedback signal in operation station is correct or not;
                           
4.2 仪表安装检查:
    Instrument installation check:
4.2.1 根据HOOK-UP图检查现场仪表管、线路安装是否正确完整,并符合相关规范及规定。
     Inspect siteinstrument piping、lineinstallation is correct and complete according to Hook-up drawing, fulfill withrelevant specification and rule.
4.2.2 仪表管路应有泄漏试验并符合要求;(同管道专业一起做泄漏试验)
     Leakage testshould be done on instrument piping and fulfill with requirement (leakage testtogether with piping specialty);
4.2.3仪表线路应做绝缘测试符合规范要求:
     Insulationtest should be done in instrument line and fulfill to specification requirement;
4.2.3.1 核对电缆规格、型号是否符合设计文件规定及进行导通检查,并用兆欧表测量其绝缘电阻,其电阻值不应小于5MΩ。
      Verify cablespecification and type, if they are fulfill design document rule, carry outbreakover check, check insulation resistance value with megameter, theresistance value should not be smaller than 5MΩ.
4.2.3.2 线路敷设完毕,应进行校线和标号;
     After completed cable pulling, line should be checked tagged;
4.21.3.3 电缆与端子连接整齐、牢固,导电良好;并进行单端接地;
       Cableconnecting with terminal should be in order、fastness, conductivity in good condition; single-end earthed;
4.2.4仪表管、线路的位号标识应清晰、方便检查,固定应牢固;
     Instrumentpiping and line position tagging should be clearness, easy to be check, firmlyfixed;
4.3 回路试验时,仪表校准点不应少于3点;
    For the instrument test, instrumentcalibration point should not be less that 3 points;
4.4 检测回路的试验应符合下列要求:
    Loop test should fulfill with the followingrequirement:
4.4.1 在检测回路的信号输入端输入模拟被测变量的标准信号,回路的显示仪表部分的示值误差不应超过回路身内各仪表允许基本误差平方和的平方根值;
     Input thestandard measured variable analog signal to be tested in signal input terminal inthe loop, the error indication in loop indication should not be bigger than theallowance intrinsic error square and square root of all instruments in theloop;
4.4.2 温度检测回路可在检测元件的输出端(温变的输出端)输入相应的模拟信号;热电阻及热电偶的检查可现场利用万用表进行;
     Temperatureloop can input relevant analog signal in test element output terminal( temperatureoutput terminal); thermal resistance and thermocouple can be done by usingmultimeter on site;
4.5 控制回路的试验应符合下列要求:
    Test for control loop should fulfill thefollowing requirement:
4.5.1 控制器和执行器的作用方向应符合设计规定;
     Controllerand actuator acting direction should fulfill design specification;
4.5.2 通过DCS系统操作站的输出向执行器发送控制信号,检查执行器执行机构在全行程范围内的动作方向和位置是否正确;
     Send controlsignal to actuator from DCS operation station, to check actuator actiondirection and position correct or not in full length of distance travel.
4.5.3 当操作站上有执行器的开度和起点、终点信号显示时,应同时进行检查和试验;
     When all openingand start point、finishedpoint indicating on actuator in operation station, check and test should bedone at the same time;
4.6 报警系统的试验应符合下列要求:
    Alarm system test should fulfill thefollowing requirement:
4.6.1 在报警回路的信号发生端模拟输入信号,检查报警灯光、音响和屏幕显示应正确;
     Input analogsignal to signal generator terminal in alarm loop, to check alarm light、sound and panel display should becorrect;
4.6.2 报警的消音、复位和记录功能应正确。
     Alarmsound acknowledge reset andrecord function should be correct.
5. 回路检查的工器具准备:
   Loop checkpreparation:
回路检查所使用仪表、仪器应在检验周期内,其精度应符合规范及设计规定。主要设备如下:
The instrument and apparatus to be used inloop check should within the checkout period, the precision should fulfillspecification and design rule. The main apparatus are as follow:
  
序号
  
No.
  
设备名称
  
Mane
规格
  
specification
单位
  
unit
数量
  
Quantity
1
数字万用表
  
Digital multimeter
  
piece
2
2
兆欧表
  
Megameter
ZC25-4A
  
piece
1
3
数字兆欧表
  
Digital megameter
  
piece
1
4
现场校验仪
  
Site checker
HC-982
  
piece
1
5
24V DC电源
  
24V dc power
APS3003S
  
piece
1
6
手操器
  
Hand operator
Hart 475/375
  
piece
1
7
精密电阻箱
  
Precision resistance box
  
piece
1
6.安全保证措施
  Security precautions
6.1严肃认真执行安全技术文件规定和要求,针对工程特点,作好安全教育和安全技术交底,牢固树立“安全第一,预防为主”的思想。
   Be strict andconscientious in execute safety specification and requirement, safety educationand safety technical hand over according to project feature, firmly buildsafety first and prevent priority.
6.2各项施工工作和施工活动必须有各项合格经过批准的程序后方可进行。特别是有特殊要求,特殊区域和  有毒有害物质和区域工作。
   Before anyconstruction and activities to be carry out, approved procedure should bepassed. Especially for special area and harmful material and area.
6.3参加施工人员,必须遵守个人防护用品的佩戴要求。高空作业者必须经健康检查并被准许进行高空作业,登高超过1.8m的高空作业者必须系安全带,安全带要求有缓冲装置,有两条带自锁挂钩的挂绳。
   The testpersonnel should follow the requirement to wear protective equipment. Workingin the high level should through health examined and approved. If the workinglevel above than 1.8m, the worker should wear safety belt with buffer deviceand two hook with self-lock.
6.4严禁设备和施工人员带病工作。使用各种器具,严格按其规程进行。
   Equipment with defectedand worker with illness is not allowed. All equipment to be used should followthe specification.
6.5施工现场严禁吸烟,施工需用的易燃易爆物品,用完后立即送回到保管地点。
   Smokingis not allowed on site, flammable and explosives should back to storage afteruse.
6.6与工艺介质相连的仪表,安装后必须关死根部阀,打开平衡阀,防止管内压力窜入仪表,造成仪表单向受压或过压损坏仪表。仪表投入运行时一定要按操作顺序进行,以免损坏仪表。
   Instrumentconnect to process media, root valve should be closed after installed, open thebalance valve to avoid the pressure get into the instrument, and cause theinstrument over pressure or damage. To avoid instrument damage, the operation procedureshould be followed before put into operation.
6.7各种仪表(器)、机具在送电前,仔细检查电源接线是否正确。
   Carefullycheck power connection is correct or not before energize any instruments.

回复

使用道具 举报

药师
 楼主| 发表于 2017-8-29 21:00:47 | 显示全部楼层
工程实施的测试比GMP确认验证测试,严谨多了!
回复

使用道具 举报

药士
发表于 2017-8-29 23:54:31 | 显示全部楼层
回复

使用道具 举报

药徒
发表于 2017-8-30 08:50:16 | 显示全部楼层
所以 药品数据管理(意见征求稿)应运而生
回复

使用道具 举报

药徒
发表于 2017-9-7 08:59:48 | 显示全部楼层
焦老师,请问一下什么情况下应该做回路测试?
我个人理解:
买回来的整机设备(例如带PLC的脉动灭菌柜)不需要回路测试了,测试基本功能可以实现就可以了;
需要现场接线的、个性化的设备(例如HVAC自控系统),这样的就需要回路测试了;
我的理由是:整机设备相当于商业化生产的成熟设备,类似于CSV的1类软件,没必要测试了,而现场接线的、个性化的设备需要检查是否有人工接线错误。
请焦老师多多指教!

点评

回路测试,基本上就是安装接线完成之后的在线测试,是基于运行环境下的输入输出测试,调试阶段必须做的。与验证无关。  详情 回复 发表于 2017-9-7 15:06
回复

使用道具 举报

药师
 楼主| 发表于 2017-9-7 15:06:14 | 显示全部楼层
Romhex 发表于 2017-9-7 08:59
焦老师,请问一下什么情况下应该做回路测试?
我个人理解:
买回来的整机设备(例如带PLC的脉动灭菌柜) ...

回路测试,基本上就是安装接线完成之后的在线测试,是基于运行环境下的输入输出测试,调试阶段必须做的。与验证无关。
回复

使用道具 举报

发表于 2020-3-6 12:00:07 | 显示全部楼层
成慧潫 发表于 2017-9-7 08:59
焦老师,请问一下什么情况下应该做回路测试?
我个人理解:
买回来的整机设备(例如带PLC的脉动灭菌柜) ...

谢谢你们的分享,对于小白来说,真的受益匪浅
回复

使用道具 举报

药生
发表于 2020-7-9 11:16:45 | 显示全部楼层
谢谢分享,非常非常有用。
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

×发帖声明
1、本站为技术交流论坛,发帖的内容具有互动属性。您在本站发布的内容:
①在无人回复的情况下,可以通过自助删帖功能随时删除(自助删帖功能关闭期间,可以联系管理员微信:8542508 处理。)
②在有人回复和讨论的情况下,主题帖和回复内容已构成一个不可分割的整体,您将不能直接删除该帖。
2、禁止发布任何涉政、涉黄赌毒及其他违反国家相关法律、法规、及本站版规的内容,详情请参阅《蒲公英论坛总版规》。
3、您在本站发表、转载的任何作品仅代表您个人观点,不代表本站观点。不要盗用有版权要求的作品,转贴请注明来源,否则文责自负。
4、请认真阅读上述条款,您发帖即代表接受上述条款。

QQ|手机版|蒲公英|ouryao|蒲公英 ( (京)-非经营性-2014-0058 京ICP证150354号 京ICP备14042168号-1 )

GMT+8, 2024-3-29 23:28

Powered by Discuz! X3.4运维单位:苏州豚鼠科技有限公司

Copyright © 2001-2020, Tencent Cloud.

声明:蒲公英网站所涉及的原创文章、文字内容、视频图片及首发资料,版权归作者及蒲公英网站所有,转载要在显著位置标明来源“蒲公英”;禁止任何形式的商业用途。违反上述声明的,本站及作者将追究法律责任。
快速回复 返回顶部 返回列表