[GMP相关] Can the HVAC of GMP clean rooms be switched off overnight?

[复制链接]
药士
发表于 2017-1-16 21:17:40 | 显示全部楼层 |阅读模式

欢迎您注册蒲公英

您需要 登录 才可以下载或查看,没有帐号?立即注册

x
仅供参考!http://pinbloggs.com/can-the-hvac-of-GMP-clean-rooms-be-switched-off-overnight/
Can the HVAC of GMP clean rooms be switched off overnight?

The ventilation / HVAC systems of clean rooms consume a lot of energy, especially power for the ventilating fan, refrigerating capacity for cooling and dehumidification in summer as well as heating for warming and steam for humidification in winter. Therefore, the question comes up again and again whether one might switch off the ventilation of the rooms overnight or when they are not used in order to save energy.
It is not advised to switch off the ventilation system completely, it is rather advised not to do it. Premises, pressure conditions, microbiology, everything would be out of control during that time. This would make the subsequent measures for the restoration of the GMP-compliant state very complex because each time a re-qualification would be necessary to reach the normal GMP-compliant state.
But a reduction in the performance of the ventilation systems (reduction of the air volume by reducing the performance of the ventilation system) is possible, and is already carried out in some companies. Here too, however, the GMP-compliant state must be achieved prior to using the clean room again and this procedure must be validated.
For this purpose the following points must be observed:
The reduction can only be carried out so far that the clean room specific limits prescribed for the relevant case are not violated in general. These limits have to be defined in each case for the operating status and the reduction mode including permissible minimum and maximum values, such as clean room class (particle count with equivalent particle size), product specific values (temperature, relative humidity), pressure conditions (pressure difference between the rooms). Note that the values in reduction mode have to be chosen in such a way that the facility has reached the GMP-compliant state in due time before production begins (integration of a time program). This state depends on different parameters such as building material and performance of the system etc. The pressure conditions should be maintained all the time, this means that a reversion of the flow direction is not allowed.
Furthermore, the installation of an independent clean room monitoring system is recommended in any case in order to constantly monitor and document the above mentioned clean room specific parameters. Thus, the conditions of the area concerned can be monitored and documented at any time. In the case of deviations (reaching of a limit) and in the individual case it is possible to access the measurement and control technology of the ventilation system and to carry out the relevant adjustments.
During the reduction attention should be paid to ensuring  that no unpredicted external interfering influences such as the entry of persons are allowed. For this the installation of a corresponding entry control is advised. In the case of an electronic locking system the entry authorisation can be linked with the above mentioned time program as well as with the independent clean room monitoring system so that entry is authorised only subject to compliance with the predefined requirements.
In principal, both states must be qualified first and then requalified in regular intervals and the customary measurements for the regular operating status such as the recovery time measurement in case of a complete failure of the facility must be carried out. In the case a clean room monitoring system exists it is in principal not required – as mentioned above – to carry out further measurements at the start of operations after reduction mode if the procedure is validated. Special focus should be put on the procedure of restarting since temporary reversions of the flow direction are possible, for instance.
All in all about 30 % of the energy costs can be saved depending on the mode of operation and the shift model but additional investment costs might have to be offset.
Reference: GMP newsdated 24-02-2016


点评

楼主这可以啊,好像在专门研究空调净化系统停机的事情: https://www.ouryao.com/forum.php?mod=viewthread&tid=348975&fromuid=155851  发表于 2017-1-17 13:03
回复

使用道具 举报

药士
发表于 2017-1-16 22:29:09 | 显示全部楼层
回复

使用道具 举报

药士
 楼主| 发表于 2017-1-16 23:55:19 | 显示全部楼层
本帖最后由 beiwei5du 于 2017-1-16 23:56 编辑

下文仅供参考!
Weekend
 Shut‐down 
of 
Validated
 Air
 Handling 
Systems
http://www.seai.ie/Your_Business/Large_Energy_Users/Special_Initiatives/Special_Working_Groups/HVAC_SWG_Spin3/Weekend_Shutdown_of_Validated_AH_Systems.pdf
关于ISO CLASS 8 cleanroom的HVAC系统周末关机的探讨:
During Spin III of the HVAC SWG, two healthcare companies who operate cGMP validated cleanrooms undertook a set of experimental procedures to facilitate the switch off of GMP AHU systems at weekends (out of production hours). This case study details the procedure followed to obtain the required data to allow weekend shutdown of Cleanroom Air Handling Systems in both of the successful facilities.




回复

使用道具 举报

药徒
发表于 2017-1-17 05:42:25 | 显示全部楼层
高端大气上档次
回复

使用道具 举报

药徒
发表于 2017-1-17 08:56:06 | 显示全部楼层
学习了解,谢谢分享
回复

使用道具 举报

药徒
发表于 2017-1-17 09:33:00 | 显示全部楼层
主要意思是可以设值班风机,但要设定相关参数及标准,进行确认。
回复

使用道具 举报

药士
 楼主| 发表于 2017-1-17 11:46:48 | 显示全部楼层
leehwadong 发表于 2017-1-17 09:33
主要意思是可以设值班风机,但要设定相关参数及标准,进行确认。

第二篇文章是直接是shut-down!
回复

使用道具 举报

药徒
发表于 2017-1-17 11:49:56 | 显示全部楼层
回复

使用道具 举报

药徒
发表于 2017-2-6 15:43:39 | 显示全部楼层
值班风机赞成,关机没必要,特别是每晚关机,第二天再开机的,这种对硬件的伤害都是无形的
回复

使用道具 举报

药神
发表于 2023-2-25 19:13:34 | 显示全部楼层
非常感谢分享
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

×发帖声明
1、本站为技术交流论坛,发帖的内容具有互动属性。您在本站发布的内容:
①在无人回复的情况下,可以通过自助删帖功能随时删除(自助删帖功能关闭期间,可以联系管理员微信:8542508 处理。)
②在有人回复和讨论的情况下,主题帖和回复内容已构成一个不可分割的整体,您将不能直接删除该帖。
2、禁止发布任何涉政、涉黄赌毒及其他违反国家相关法律、法规、及本站版规的内容,详情请参阅《蒲公英论坛总版规》。
3、您在本站发表、转载的任何作品仅代表您个人观点,不代表本站观点。不要盗用有版权要求的作品,转贴请注明来源,否则文责自负。
4、请认真阅读上述条款,您发帖即代表接受上述条款。

QQ|手机版|蒲公英|ouryao|蒲公英 ( 京ICP备14042168号-1 )  京ICP证150354号  互联网药品信息服务证书编号: (京)-非经营性-2024-0033

GMT+8, 2024-9-21 11:11

Powered by Discuz! X3.4运维单位:苏州豚鼠科技有限公司

Copyright © 2001-2020, Tencent Cloud.

声明:蒲公英网站所涉及的原创文章、文字内容、视频图片及首发资料,版权归作者及蒲公英网站所有,转载要在显著位置标明来源“蒲公英”;禁止任何形式的商业用途。违反上述声明的,本站及作者将追究法律责任。
快速回复 返回顶部 返回列表