在ISPE《GOOD PRACTICE GUIDE Technology Transfer (Third Edition) 》中提到:
water run:
3.4 Operational Readiness
“……Testing of full scale manufacturing equipment to ensure proper function, e.g., mixing studies, buffer or water runs,cleaning studies, etc.”
Engineering run:
5.2.4 At Scale Process (Procedure) Evaluation and Qualification
“…… Engineering runs are defined here as trial full scale runs performed in the same equipment to be used for GMPmanufacturing using the intended procedures and without the intent to be released for use. ……”